Building Updates

Building Updates

Learn more about our new building project timeline and progress.

Watch our progress:

March 16, 2026 Phase 4a- Purchase of Wall Insulation
May 18, 2026- Fundraising for interior framing

Latest Update

2/16/2026- The contractor installing the steel structure started on December 1st to erect the building and is making good progress despite heavy winds and some snow. The exterior structure of the building is complete and next is interior wall insulation.

3/23/2026- Fundraising Update: We have completed the steel structure and our building is ‘dried in’. Fundraising for the interior wall insulation is complete (Thanks to God helping us with the Italian Breaking Bread FUN-raiser Meal. Insulation has been ordered and when it is here we will install it.

5/18/2026- Fundraising for our interior Framing has begun. This will include the materials for main and upper level wall web trusses and framing so rough-in electrical and plumbing (the next parts of this phase) can be done. This portion of the next phase is estimated to cost $72,450. To date we have raised $9,199 (about 12%) of that. While we’re raising these finances we are skim-coating and dying the portion of the floor concrete that will be a final finish.

Next Milestone

Our next milestone will be when we get the concrete floor dyed and the interior wall insulation installed and ready for interior framing.

Current Phase of Construction

We are into “Phase 4” of construction.

Phase 1 – Planning, engineering & steel building structure [completed & paid for]

Phase 2 – Underground utilities, footings, and floor slab [completed & paid for with part of a loan]

Phase 3 – Building erection including insulation, doors & windows [completed except for wall insulation]

Phase 4 – Wall insulation, dying of the concrete as flooring, 2nd level & interior framing

Phase 5 – Vestibule (front entry doors), rough-in for plumbing, electric and heating & air conditioning, Connection Corridor, Interior sheetrock & finishes

Phase 6 – Parking, water, and septic system

Phase 7 – Media, furniture, kitchen and elevator

Next Funding Goal

We have completed phase 4a fundraising of roughly $22,075 to purchase the wall insulation. The insulation has been ordered so we can install it and then begin fundraising for interior framing materials.

Volunteers

To volunteer, please click the button below so we can understand your schedule and how to best make use of your unique skills.